Key findings of report include:
- tram fleet is ageing and needs an overhaul
- risk to safety and service delivery with older trams
- by end of contract in 2024, all trams over 20 years old (about 78%) would have exceeded by dates
- ageing workforce with specific knowledge of tram network, around 30%, expected to retire within 10 years
Operation of tram network costs about $2.7 billion over 7 years.