Report of Committee Meetings 14th November 1978

Works Committee
Two Days Have Been Lost Due To Bad Weather
West Road Footpath 75% Completed
Braybrook Area Footpath Work is Progressing
Macedon Street Kerb & Channell 80% Completed
McIntyre Road South of Bridge Kerb & Channell 80% Completed
McIntyre Road South of Bridge Road Works Delayed Due to No Supply of Bitumen
Cullin Street Road Works Delayed Due to No Supply of Bitumen
Petrol Storage for Mowers Is Causing Issues
The Sealing of Concrete Wickets with Laycol not yet completed
Fire Hazard Gangs have commenced removing fire hazards
Council Surveyors have carried out initial survey of Castley Reserve
Swimming Pool completion date 22nd November 1978 but still could be delayed due to connection of gas and commissioning time
Bon Thomas Reserve and Diamond Avenue Reserve progress is slow due to vandalism and supply of rubber gaskets
Orama Street Pre-School and Child Care Centre concrete slab has been poured
Highpoint West site works begin this week
Toilets on Reserves nearing completion with the exception of Selwyn Park
Steps are being taken to minimise the fuel storage during the current T.W.U. stoppage

Report of the Finance Committee

Report of the Town Clerk
Proposed Hostel for Failed Aged Request for Financial Assistance
Tenders for Vending Machines Sunshine Swimming Pool
Overpayment of Gratuities

Report of the City Engineer
Soil Sterilizer Nursery
Replacement of Sweeper No 123
Bon Thomas Resereve Pre-School Centre
Neale Road Construction (North Carriageway)
Application to Country Roads Board for Funds for the Year Ending 30th June 1980