Report of Committee Meetings 3rd October 1978
Works Committee
Macedon Street Drain is Complete
Tree Planting 99.5% Complete
Gypsum Delivered to Reserves
Little Athletics Track at Parsons Reserve Top Dressed and Sown Down
Dempster Park Practice Wickets Minor Works to be Completed
Bon Thomas Reserve & Diamond Reserve Buildings / Steel Frames Completed
Orama Street Slab being poured this week
Selwyn Park Toilet Block Construction Underway
Swimming Pool Builder's Claim has not been Settled
Highpoint Infant Welfare Centre Suggestions have been verbally approved
Finance Committee
Finalisation of Loan Schedule
Subjects
- city of sunshine,
- alexander "alex" george gillon,
- macedon street,
- maidstone,
- parsons reserve,
- stanford street,
- sunshine,
- dempster park,
- phoenix street,
- sunshine north,
- bon thomas reserve,
- quinn street,
- deer park,
- diamond reserve,
- diamond avenue,
- albanvale,
- orama street,
- st. albans,
- selwyn park,
- selwyn street,
- albion,
- highhpoint infant welfare centre,
- rosamond road,
- maribyrnong