Administrative record - City of Sunshine - Commissioner Mr Alexander Alex George Gillon Collection 1976 - 1982 - Report of works committee meeting 10th March 1981, City of Sunshine, 10th March 1981

Archive (collection) - Commissioner Mr Alexander Alex George Gillon Collection

Physical description

Foolscap sized document.

Inscriptions & markings

Report of Works Committee Meeting 10th March 1981

Pennell Reserve Pavilion brick work completed
Municipal Offices work on the linkway has been delayed following a New South Wales plumbers ban affecting the contractor
Ralph Street Reserve Pavilion it is anticipated that the steel work will be erected this week
Cranwell Park Toilets progress delayed following a flood resulted from a burst M.M.B.W. water main
Cherry Crescent Child Care Centre the slab required to be re-laid in parts as a result of the kerb and channel not being constructed at the levels indicated the drawings
Kerb & Channel Lily Street Braybrook completed including crossings. Pavement work will commence when a gang is available
Kerb & Channel Andrew Street Sunshine near completion
Wallace Street reconstruction work has been discontinued as per Forward Planning Committee Meeting 3rd March 1981
King Edward Avenue Albion the footpath between Sydney Street and Adelaide Street is 50% complete
Braybrook Area two gangs continue to work in this area
Churchill Avenue / Mitchell Street Maidstone the access lane presently under construction it to provide residents in the Omar Street area with access to Ballarat Road