Report of Committee Meetings 29th September 1980

Report of the Works Committee Meeting
Kerb & Channel Fisher Street Maidstone completed
Kerb & Channel Robinsons Road Deer Park to commence
Kerb & Channel Duke Street Sunshine 70% complete on western side
Footpath Ballarat Road Maidstone Omar Street to Rosamond Road completed
Footpath Phoenix Street Sunshine North commenced
Footpath Ashley Street Maidstone completed
Footpath Ballarat Road Maidstone Area in progress
Drainage Cranwell Street Braybrook commenced
Road Work Duke Street Sunshine excavated between Lily Street and Devonshire Road. Section between Hertford Road and Ballarat Road has commenced
Road Work Fisher Street Maidstone and Billingham Road Deer Park ready for asphalting
Tree Planting bulk planting completed. Single planting approximately two weeks to complete
Tree Pruning gang working on S.E.C. list. Travel crane will then be hired for remaining work
Cricket Pitches all turf wickets have been top dressed
Robert Barrett Reserve concrete being poured
Errington Reserve old concrete pitches to be removed and re-laid this week
Practice Wickets for I.C.I. Oval expected to be delivered this week
Football Grounds goal areas have now been top dressed and reseeded
Weed Spraying Programme delayed as the result of continual strong winds
Scovell Reserve and Maribyrnong Reserve quotations being obtained for repairs to practice nets
Sassella Park excavated to be ready for the 1981 hockey season
Albion Tennis Club Pavilion building completed. Drainage and car parking are subject to Finance Committee
Aycliffe Drive Infant Welfare & Pre-School Centre building completed and ready for occupation
Depot Workshop steel worked expected to be erected later this week
Pennell Reserve Pavilion anticipated that work will commence next week
Municipal Offices progressing satisfactorily
Ralph Street Reserve Pavilion no objections have been received against our application
Cranwell Park Toilets slab to be poured next week
Cherry Crescent Child Care Centre Building tenders received
Tallintyre Reserve Building concern was expressed at the desirability of erecting a new building when Council is having continual problems with the vandalization of the toilet block
Bitumen Surfacing this contract is now completed
Ashley Street nature strips only require attention
Westerngate Drain problems with rock and clay
Bon Thomas Reserve drainage and water reticulation to be laid
St. Albans Road kerb & channel completed

Report of the Finance Committee Meeting

Report of the Town Clerk
Payment for Driver's Licence Fee Officers and Employees

Report of the City Engineer & Planner
Albion Tennis Club Pavilion
Sewerage Facilities Ralph Street Reserve
Bon Thomas Reserve Pre-School Centre Sewerage Treatment Plant and Effluent Disposal Unit
Orama Street Child Care Centre Sewerage Treatment Plant and Effluent Disposal Unit
Aycliffe Avenue Pre-School and Infant Welfare Centre landscaping and car parking

Report of the Forward Planning Committee Meeting

Sunshine Tip Hours of Operation
St. Albans Cricket Club requesting attention to the practice nets